Project Owner:
Jacobs /MTA
Services: Construction Inspection
VN Engineers, Inc. was a subconsultant to Jacobs Engineering on this project. Contract HH-80 consisted of the replacement of the lower level deck and the installation of an AASHTO Compliant bicycle path on the Henry Hudson Bridge which is a two-level fixed steel arch structure. The project scope included inspection of the following project objectives: south approach (bents 1 to 8), steel-supported span (bents 8-21), and the north approach (bents 21-39).
Objectives included the installation of a new concrete deck, installation of galvanized steel structures, and the replacement of curb stringers. Duties included general inspection of the furnishing, testing, and installation of concrete, bearings, under deck protective shielding, and platforms. Additional inspection of the furnishing, fabricating and installation of the new bridge drainage system, an armorless joint system, the new safety shape barriers, all electrical work, and abatement of LCM.